GROUNDWORKS
Crocker Build have undertaken a number of groundworks projects in Guernsey – see below for the details. We also do hard landscaping, driveways and private parking as part of new build or extension contracts – please contact us for more details.
Delancey Lane
Client: Riverside Point (Gsy) Ltd
Development of 4 new residential dwellings:
Groundworks
Foundations
Blockwork and drainage
Demolition works to remove 8 chalet units and garage
Foundations: 124 linear metres
Concrete slab: 152 square metres (200mm) C35N
Cavity concrete blockwork: 415 square metres
Foul and surface water drainage: 102 linear metres and 2 soakaways
Duration: 4 months
North Clifton Residential Development
Client: Rico Developments Ltd
Reinforced concrete basement carpark:
Piling
Underpinning
622 tonnes of C40 shuttered concrete
44 tonnes of reinforcement
Steel and mass concrete temporary works to granite Retaining Wall
16 nr. 350mm dia. augured piles
Miscellaneous drainage
Duration: 6 months
Vine House, St Martins
Client: Private
Stabilisation of challenging terraced garden and landscaping:
Excavation of terracing
Bulk removal of ground
Timber sleepers
Granite walls and steps
Blockwork and external rendering
Landscaping
Duration: 3 months
Jardin des Roches, Vale
Client: Private
Removal of existing swimming pool, groundworks and landscaping of garden:
Removal of old swimming pool and associated M&E pipework, electrics, etc.
Infilling and compacting groundworks
Concrete slab and paving
Blockwork and brickwork
Landscaping
Duration: 2 months
Island House Car Park, Grande Rue, St Martins
Client: Sandpiper C.I. Ltd.
Construction of new car park and associated drainage and lighting works:
Tarmac surfacing: 1,900 metres square
Hardcore stone base: 570 cubic metres
Installation of 3-stage petrol interceptor
Installation of 350 nr. polystorm soakaway units
Kerbing: 160 metres
Electrical ducting: 220 metres
Duration: 3 months
Guernsey Tennis Centre Car Park
Client: Guernsey Tennis Centre
Construction of a new car park and access
road plus associated drainage and construction of Guernsey earth banks.
Duration: 3 months
Cobo Coastal Defence
Client: Environment Department, States of Guernsey
Remedial works to German casemate bunker to provide a long term coastal defence:
Reinforced concrete demolition: 450 cubic metres
In-situ concrete: 420 cubic metres
Reinforcement: 20 tonnes
Installation of rock anchors
Tidal working conditions
Duration: 2 months
Castel Farm Eggs
Client: Castel Farm Eggs
Removal of the existing reinforced concrete slab and construction of a new slab with mass concrete pad foundations for new barn:
Excavation and breaking up of old concrete slab
Grade C35N concrete slab: 155 square metres
Powerfloat finish
Plate load deflection testing to foundations
Duration: 1 month
Captains Hotel, St Martins
Client: Lapwing Ltd
Drainage and tanking works to remedy severe damp problems and water ingress experienced by basement kitchen:
Tanking
Concrete retaining walls
Foul and surface water drainage works
Excavation to expose existing walls
Mass concrete shuttered walls
Bituthene tanking installed to walls
Extensive foul and surface water drainage carried out
Duration: 1 month
Houmet Housing Scheme
Client: Phoenix Construction Ltd
Installation of new foul water package pumping station and 90mm diameter rising main:
Excavation and shoring
Installation of dual vortex package pumping station
(Edincare Magnagrand 4,500 litre)
Mechanical, electrical and commissioning works to station
Conduit, control kiosk and landscaping works
Duration: 1 month

Client: Riverside Point (Gsy) Ltd



Client: Riverside Point (Gsy) Ltd
OTHER PROJECTS